Published monthly · register snapshot 18 Sep 2026 · method v1.1

Pinly Filing Index — Karnataka

What the Karnataka RERA public register shows across all 8,919 registrations as of 18 Sep 2026: how many filed a quarterly progress update for each quarter since 1 Oct 2025, how many are past the completion date they filed, and how many still have approvals pending. Counts only — no builder is named or ranked here; each project's own record is on its page.

63.8%

Quarterly update filed for Q1 2026-27

1,627 of 2,550 registrations expected to file for Apr–Jun 2026.

6,228

Past filed completion date, no occupancy certificate read

Of 8,818 approved registrations. A passed date alone does not mean a delay.

250

Registrations with approvals pending

540 approvals not yet shown as approved, 428 of them “to be applied”, in the latest NOC filings.

Quarterly updates, by quarter

Builders registered with Karnataka RERA file a progress update every quarter. Pinly shows when each update appeared on the register; a quarter with no update on the register is shown as not filed. A quarter is counted once its update was due on or before the snapshot date. “Expected” means an approved registration inside its own filed timeline, plus any registration that filed anyway.

QuarterFiledExpectedShare
Q3 2025-26 (Oct–Dec 2025)1,8002,81364%
Q4 2025-26 (Jan–Mar 2026)1,6692,56365.1%
Q1 2026-27 (Apr–Jun 2026)1,6272,55063.8%

By district

The 10 districts with the most registrations, largest first. Order is by size, not by any measure of filing.

DistrictRegistrationsUpdate filed, Q1 2026-27Past filed completion, no OC readApprovals pending
Bengaluru Urban4,098910 of 1,257 (72.4%)2,785103
Mysore70297 of 164 (59.1%)54133
Bengaluru Rural656190 of 249 (76.3%)39428
Dakshina Kannada611134 of 180 (74.4%)42723
Belagavi45953 of 117 (45.3%)3393
Udupi26045 of 74 (60.8%)1746
Dharwad24640 of 61 (65.6%)1823
Ballari2285 of 28 (17.9%)1941
Kalaburagi22220 of 33 (60.6%)18914
Tumakuru20614 of 97 (14.4%)964

How to read this

  • Every count is of filings as they appear on the register on 18 Sep 2026; filings made after that date are not counted.
  • Pinly does not say whether an update was late; the K-RERA deadline is being confirmed first. “Not filed” means no update for that quarter on the register.
  • “Past filed completion date” compares the completion date the promoter filed with the snapshot date. Pinly has not read occupancy certificates for every project, and a project may have received one, or an extension, that is not yet on the register.
  • Approvals counts come from each registration's latest NOC filing: approvals shown as approved out of those applicable.