NEW Haven Bengaluru

NEW Haven Bengaluru

Filed completion date passed

by Smart Value Homes (Peenya Project) Private LimitedBengaluru North 560041

Apartments · 188 units · 3 RERA registrations

Construction progress

No progress figure filed yet

The register carries no quarterly progress update with a completion % for this project.

Filing record

Free · facts from the K-RERA register, no grade

Quarterly updates
—none due yet on the register
Completion date filed
30 Sep 2023latest phase · a date has passed
See every filing · 6 lines, each linked to its source · 3 registrationsHide the filings

Pinly Filing Record · free

NEW HAVEN BENGALURU PHASE II

What was filed with Karnataka RERA and when, each linked to the filing. Facts only — no grade, no score. Registration PRM/KA/RERA/1251/309/PR/170916/000146.

  • Quarterly progress updates

    K-RERA register ↗

    Not counted: the filed completion date (31 Dec 2019) is before 1 Oct 2025, when quarterly updates begin on the register.

  • Completion date

    K-RERA register ↗

    Filed completion date 31 Dec 2019 has passed. Pinly has not yet read an occupancy certificate for this project.

Builders registered with Karnataka RERA file a progress update every quarter. Pinly shows when each update appeared on the register; a quarter with no update on the register is shown as not filed. Quarters before 1 Oct 2025 are not counted — the register carries no quarterly updates before then.

As of 18 Sep 2026 (Pinly's copy of the Karnataka RERA register). Machine-read from filings. Spot an error? Send a correction →

Pinly Filing Record · free

New Haven Bengaluru Phase IV

What was filed with Karnataka RERA and when, each linked to the filing. Facts only — no grade, no score. Registration PRM/KA/RERA/1251/309/PR/200103/003103.

  • Quarterly progress updates

    K-RERA register ↗

    Not counted: the filed completion date (28 Feb 2022) is before 1 Oct 2025, when quarterly updates begin on the register.

  • Completion date

    K-RERA register ↗

    Filed completion date 28 Feb 2022 has passed. Pinly has not yet read an occupancy certificate for this project.

Builders registered with Karnataka RERA file a progress update every quarter. Pinly shows when each update appeared on the register; a quarter with no update on the register is shown as not filed. Quarters before 1 Oct 2025 are not counted — the register carries no quarterly updates before then.

As of 18 Sep 2026 (Pinly's copy of the Karnataka RERA register). Machine-read from filings. Spot an error? Send a correction →

Pinly Filing Record · free

NEW HAVEN BENGALURU PHASE V

What was filed with Karnataka RERA and when, each linked to the filing. Facts only — no grade, no score. Registration PRM/KA/RERA/1251/309/PR/290822/005198.

  • Quarterly progress updates

    K-RERA register ↗

    Not counted: the filed completion date (30 Sep 2023) is before 1 Oct 2025, when quarterly updates begin on the register.

  • Completion date

    K-RERA register ↗

    Filed completion date 30 Sep 2023 has passed. Pinly has not yet read an occupancy certificate for this project.

Builders registered with Karnataka RERA file a progress update every quarter. Pinly shows when each update appeared on the register; a quarter with no update on the register is shown as not filed. Quarters before 1 Oct 2025 are not counted — the register carries no quarterly updates before then.

As of 18 Sep 2026 (Pinly's copy of the Karnataka RERA register). Machine-read from filings. Spot an error? Send a correction →

Full report · NEW Haven Bengaluru

₹999+ GST

The free record shows what was filed. The report reads it for you:

  • Money collected from buyers and withdrawn, quarter by quarter, and what the RERA Act requires
  • Approved-plan data where read: FAR, ground coverage, setbacks, unit counts
  • Sale-agreement clauses that favour the builder, flagged (where the agreement has been read)
  • The builder's record across all its other projects
Get the full report — ₹999

See a sample report · 3 more inside

₹999 + 18% GST, one project, until possession. No builder can pay to change what it says.

Watch NEW Haven Bengaluru

Get an email when this project files something new — a quarterly update, a completion-date change, an approval. Free. Alerts start soon.

Every alert will carry a one-click unsubscribe. To stop before then, or to have your email deleted, use the contact on our privacy page. Privacy

No photographs of NEW Haven Bengaluru on Pinly yet — only what was filed with K-RERA.

Price · from the developer

Price on request

Pinly holds no published price and does not estimate one. Ask the developer for the price sheet.

Type
Apartments
Units (filed)
188

Location

Bengaluru North 560041 · about 22 km NW of MG Road (straight line)

13.10193, 77.44329 · from the RERA filingOpenStreetMapGoogle Maps

What was filed with K-RERA

The promoter's own words and site details, as filed — not edited by Pinly.

Residential development project (Tower Nos. 30, 31, 32, 33 & 34) situated at Survey No.3/2,3/3,4/2,2/3,2/4 at Sheshagiriraopalya village, Dasanapura Hobli, Bangalore North Taluk.

Site address (as filed)
Survey No.3/2,3/3,4/2,2/3,2/4 at Sheshagiriraopalya village, Dasanapura Hobli, Bangalore North Taluk.
Taluk · district
Bengaluru North · Bengaluru Urban
PIN
560041
Land (filed)
6.22 acres
Towers / blocks (filed)
4

RERA facts

From the Karnataka RERA register — NEW Haven Bengaluru is registered in 3 phases.

  • NEW HAVEN BENGALURU PHASE II

    PRM/KA/RERA/1251/309/PR/170916/000146

    Approved
    Approved
    16 Sep 2017
    Proposed completion
    31 Dec 2019
    Construction
    No quarterly filing
    Units
    —
  • New Haven Bengaluru Phase IV

    PRM/KA/RERA/1251/309/PR/200103/003103

    Approved
    Approved
    3 Jan 2020
    Proposed completion
    28 Feb 2022
    Construction
    No quarterly filing
    Units
    —
  • NEW HAVEN BENGALURU PHASE V

    PRM/KA/RERA/1251/309/PR/290822/005198

    Approved
    Approved
    29 Aug 2022
    Proposed completion
    30 Sep 2023
    Construction
    No quarterly filing
    Units
    188

The register is the authority. Check the number and the promoter’s name on the K-RERA portal before you pay.

Cite: Pinly, NEW Haven Bengaluru (PRM/KA/RERA/1251/309/PR/170916/000146, PRM/KA/RERA/1251/309/PR/200103/003103, PRM/KA/RERA/1251/309/PR/290822/005198), Karnataka RERA filings as of 18 Sep 2026, method v1.1. https://pinly9.khosha.tech/projects/new-haven-bengaluru-bengaluru-north