Apartments · 336 units · 1 RERA registration

Construction progress · as filed with K-RERA

100%complete

Filed for Q1 2026-27 (Apr–Jun 2026)
on 15 Jul 2026 · Filing ↗

The promoter’s own figure from its quarterly update, not inspected by Pinly.

Filing record

Free · facts from the K-RERA register, no grade

Quarterly updates
3 of 3filed · none missing
Completion date filed
13 Jun 2026date has passed
CA certificate
Attachedto the latest update
See every filing · 4 lines, each linked to its sourceHide the filings

Pinly Filing Record · free

Every filing, line by line

What was filed with Karnataka RERA and when, each linked to the filing. Facts only — no grade, no score. Registration PRM/KA/RERA/1251/446/PR/210324/006717.

  • Quarterly progress updates

    All filedFiling ↗

    3 of 3 filed — quarters due since 1 Oct 2025, as of 18 Sep 2026. (15 Jul 2026)

    Quarter by quarter (3)
    • Q3 2025-26 (Oct–Dec 2025)Quarter ended 31 Dec 2025. Filed 23 Feb 2026 (54 days after quarter end).
      FiledFiling ↗
    • Q4 2025-26 (Jan–Mar 2026)Quarter ended 31 Mar 2026. Filed 15 Apr 2026 (15 days after quarter end).
      FiledFiling ↗
    • Q1 2026-27 (Apr–Jun 2026)Quarter ended 30 Jun 2026. Filed 15 Jul 2026 (15 days after quarter end).
      FiledFiling ↗
  • Completion date

    K-RERA register ↗

    Filed completion date 13 Jun 2026 has passed. Its latest quarterly update (Q1 2026-27) reports 100% complete. Pinly has not yet read an occupancy certificate for this project.

  • CA certificate (latest quarter)

    FiledFiling ↗

    A chartered accountant's certificate is attached to the Q1 2026-27 update. (15 Jul 2026)

  • Construction progress

    Filing ↗

    100% complete, as filed for Q1 2026-27 (Apr–Jun 2026) on 15 Jul 2026. The promoter's own figure.

Builders registered with Karnataka RERA file a progress update every quarter. Pinly shows when each update appeared on the register; a quarter with no update on the register is shown as not filed. Quarters before 1 Oct 2025 are not counted — the register carries no quarterly updates before then.

As of 18 Sep 2026 (Pinly's copy of the Karnataka RERA register). Machine-read from filings. Spot an error? Send a correction →

Full report · Devagiri Opal

₹999+ GST

The free record shows what was filed. The report reads it for you:

  • Money collected from buyers and withdrawn, quarter by quarter, and what the RERA Act requires
  • Approved-plan data where read: FAR, ground coverage, setbacks, unit counts
  • Sale-agreement clauses that favour the builder, flagged (where the agreement has been read)
  • The builder's record across all its other projects
Get the full report — ₹999

See a sample report · 3 more inside

₹999 + 18% GST, one project, until possession. No builder can pay to change what it says.

Watch Devagiri Opal

Get an email when this project files something new — a quarterly update, a completion-date change, an approval. Free. Alerts start soon.

Every alert will carry a one-click unsubscribe. To stop before then, or to have your email deleted, use the contact on our privacy page. Privacy

No photographs of Devagiri Opal on Pinly yet — only what was filed with K-RERA.

Price · from the developer

Price on request

Pinly holds no published price and does not estimate one. Ask the developer for the price sheet.

Type
Apartments
Units (filed)
336

Location

Bengaluru East 560067 · about 15 km E of MG Road (straight line)

13.00237, 77.73613 · from the RERA filingOpenStreetMapGoogle Maps

What was filed with K-RERA

The promoter's own words and site details, as filed — not edited by Pinly.

Construction of single dwelling or multi dwelling or multistoried residential buildings

Site address (as filed)
No.1269, Devagiri Opal, Sy No.30/1, 30/2, 30/4, Sadaramangala Village , Kodigehalli Rd, K R Puram Hobli , Bengaluru East , Bengaluru Urban, Karnataka - 560067
Taluk · district
Bengaluru East · Bengaluru Urban
PIN
560067
Towers / blocks (filed)
8

RERA facts

From the Karnataka RERA register.

  • DEVAGIRI OPAL

    PRM/KA/RERA/1251/446/PR/210324/006717

    Approved
    Approved
    21 Mar 2024
    Proposed completion
    13 Jun 2026
    Construction
    100% · Q1 (2026-27)
    Units
    336

The register is the authority. Check the number and the promoter’s name on the K-RERA portal before you pay.

Cite: Pinly, Devagiri Opal (PRM/KA/RERA/1251/446/PR/210324/006717), Karnataka RERA filings as of 18 Sep 2026, method v1.1. https://pinly9.khosha.tech/projects/devagiri-opal