Karnataka RERA compliance scorecard

Jrc Projects

B

71.3/100 · Mostly compliant

As of 8 Sep 2026, Jrc Projects holds a Pinly RERA Compliance grade of B (71.3/100) across 8 Karnataka RERA registrations.

It ranks 163 of 295 graded builders and scores higher than 30% of all developers scored.

RERA registrations
8
Approved
8
Rank (graded builders)
163 of 295
Districts
1

Registered in Bengaluru Urban.

How the score is made up

Five checks, each the share of Jrc Projects's own registrations that pass it. Weights: delivers on the promised date 30%, withdrawals in line with collections 20%, files quarterly progress updates 25%, reports progress consistently 10%, registration in good standing 15%. Checks that don't apply are left out and the rest re-weighted; small counts are blended toward the state average (2 pseudo-registrations). Full methodology.

  1. Delivers on the promised date

    100% compliant · 25.0 of 30.0 pts

    1 of 1 registration due between 1 Oct 2025 and 8 Sep 2026 were reported 100% complete in the developer's own update after the due date.

    Blended toward the state average: 100% on its own filings → 83% used in the score.

  2. Withdrawals in line with collections

    67% compliant · 12.3 of 20.0 pts

    2 of 3 registrations with quarterly money filings showed withdrawals from the project account in line with collections; 1 counted against (a borderline quarter counts half).

    Blended toward the state average: 67% on its own filings → 62% used in the score.

  3. Files quarterly progress updates

    33% compliant · 10.5 of 25.0 pts

    1 of 3 running registrations approved before 1 Oct 2025 have filed a quarterly progress update; 2 show none on the register.

    Blended toward the state average: 33% on its own filings → 42% used in the score.

  4. Reports progress consistently

    100% compliant · 8.8 of 10.0 pts

    1 of 1 registration with two or more quarterly updates reported progress that moved forward.

    Blended toward the state average: 100% on its own filings → 88% used in the score.

  5. Registration in good standing

    100% compliant · 14.8 of 15.0 pts

    8 of 8 registrations are in good standing — none revoked, withdrawn or with contradictory dates.

    Blended toward the state average: 100% on its own filings → 98% used in the score.

Source: Karnataka RERA public register (rera.karnataka.gov.in), snapshot 18 Sep 2026. Scores as of 8 Sep 2026, method v1.0 — how this is calculated. A grade is a signal from the developer's own public filings, not a legal finding.

Registrations 8

As filed with Karnataka RERA, newest approval first.

ProjectDistrictTypeStatusProposed completion
Jrc KansoBengaluru UrbanResidential/Group HousingApproved28 Mar 2031
Jrc Wild Woods Phase IiiBengaluru UrbanResidential/Group HousingApproved10 Nov 2028
Jrc SanzioBengaluru UrbanResidential/Group HousingApproved31 Dec 2027
Jrc Wild Woods Building 2Bengaluru UrbanResidential/Group HousingApproved20 Mar 2028
Jrc Palladio Phase 2Bengaluru UrbanPlotted DevelopmentApproved30 Dec 2023
Jrc Wild WoodsBengaluru UrbanResidential/Group HousingApproved30 Mar 2026
Jrc PalladioBengaluru UrbanResidential/Group HousingApproved27 Mar 2026
PalladioBengaluru UrbanPlotted DevelopmentApproved31 Jan 2020

Jrc Projects — questions buyers ask

Is Jrc Projects registered with Karnataka RERA?

Yes. As of 8 Sep 2026, Jrc Projects appears as the promoter on 8 registrations on the Karnataka RERA public register — 8 approved, in Bengaluru Urban. Source: Karnataka RERA public register, snapshot 18 Sep 2026.

Is Jrc Projects RERA compliant?

Jrc Projects holds a Pinly RERA Compliance grade of B (71.3/100, "Mostly compliant") as of 8 Sep 2026, computed only from its own filings with Karnataka RERA. Its weakest area is "files quarterly progress updates": 1 of 3 running registrations approved before 1 Oct 2025 have filed a quarterly progress update; 2 show none on the register. The grade is a signal from public filings, not a legal finding.

How many projects has Jrc Projects registered with Karnataka RERA?

8 as of 8 Sep 2026, the earliest approved in 2018 and the latest in 2026. Source: Karnataka RERA public register, snapshot 18 Sep 2026.

Are Jrc Projects's projects delayed?

1 of 1 registration due between 1 Oct 2025 and 8 Sep 2026 were reported 100% complete in the developer's own update after the due date. Completion dates before 1 Oct 2025 are not judged, because the register has no quarterly updates before then to tell a finished project from a late one.

Does Jrc Projects file quarterly progress reports with RERA?

1 of 3 running registrations approved before 1 Oct 2025 have filed a quarterly progress update; 2 show none on the register.

Is this wrong? Request a correction

Every number here comes from filings on the Karnataka RERA register. If a filing was misread, a status has changed or a registration belongs to someone else, tell us — with a link to the filing if you have one. We review every request, fix errors at the next refresh and note the change in the methodology changelog. Developers are welcome to write in about Jrc Projects.