Karnataka RERA compliance scorecard
Bsr Projects
78.1/100 · Mostly compliant
As of 8 Sep 2026, Bsr Projects holds a Pinly RERA Compliance grade of B (78.1/100) across 4 Karnataka RERA registrations.
It ranks 49 of 295 graded builders and scores higher than 41% of all developers scored.
- RERA registrations
- 4
- Approved
- 4
- Rank (graded builders)
- 49 of 295
- Districts
- 1
Registered in Bengaluru Urban.
How the score is made up
Five checks, each the share of Bsr Projects's own registrations that pass it. Weights: delivers on the promised date 30%, withdrawals in line with collections 20%, files quarterly progress updates 25%, reports progress consistently 10%, registration in good standing 15%. Checks that don't apply are left out and the rest re-weighted; small counts are blended toward the state average (2 pseudo-registrations). Full methodology.
Delivers on the promised date
Not applicable · weight 30% re-shared
No registration had its promised completion date between 1 Oct 2025 and 8 Sep 2026 with a quarterly update to judge it by, so this component is left out and its weight is shared across the others.
Withdrawals in line with collections
75% compliant · 21.5 of 33.3 pts
1.5 of 2 registrations with quarterly money filings showed withdrawals from the project account in line with collections; 0.5 counted against (a borderline quarter counts half).
Blended toward the state average: 75% on its own filings → 64% used in the score.
Files quarterly progress updates
100% compliant · 32.2 of 41.7 pts
2 of 2 running registrations approved before 1 Oct 2025 have filed a quarterly progress update.
Blended toward the state average: 100% on its own filings → 77% used in the score.
Reports progress consistently
Not applicable · weight 10% re-shared
No registration has two or more quarterly updates yet, so this component is left out and its weight is shared across the others.
Registration in good standing
100% compliant · 24.4 of 25.0 pts
4 of 4 registrations are in good standing — none revoked, withdrawn or with contradictory dates.
Blended toward the state average: 100% on its own filings → 97% used in the score.
Source: Karnataka RERA public register (rera.karnataka.gov.in), snapshot 18 Sep 2026. Scores as of 8 Sep 2026, method v1.0 — how this is calculated. A grade is a signal from the developer's own public filings, not a legal finding.
Registrations 4
As filed with Karnataka RERA, newest approval first.
| Project | District | Type | Status | Proposed completion |
|---|---|---|---|---|
| Daintree 3 | Bengaluru Urban | Plotted Development | Approved | 28 Feb 2027 |
| Natura Daintree - Ii | Bengaluru Urban | Residential/Group Housing | Approved | 2 Jan 2027 |
| Dain Tree | Bengaluru Urban | Plotted Development | Approved | 1 Sep 2025 |
| Zest | Bengaluru Urban | Residential/Group Housing | Approved | 15 Mar 2022 |
Bsr Projects — questions buyers ask
Is Bsr Projects registered with Karnataka RERA?
Yes. As of 8 Sep 2026, Bsr Projects appears as the promoter on 4 registrations on the Karnataka RERA public register — 4 approved, in Bengaluru Urban. Source: Karnataka RERA public register, snapshot 18 Sep 2026.
Is Bsr Projects RERA compliant?
Bsr Projects holds a Pinly RERA Compliance grade of B (78.1/100, "Mostly compliant") as of 8 Sep 2026, computed only from its own filings with Karnataka RERA. Its weakest area is "withdrawals in line with collections": 1.5 of 2 registrations with quarterly money filings showed withdrawals from the project account in line with collections; 0.5 counted against (a borderline quarter counts half). The grade is a signal from public filings, not a legal finding.
How many projects has Bsr Projects registered with Karnataka RERA?
4 as of 8 Sep 2026, the earliest approved in 2019 and the latest in 2024. Source: Karnataka RERA public register, snapshot 18 Sep 2026.
Are Bsr Projects's projects delayed?
No registration had its promised completion date between 1 Oct 2025 and 8 Sep 2026 with a quarterly update to judge it by, so this component is left out and its weight is shared across the others. Completion dates before 1 Oct 2025 are not judged, because the register has no quarterly updates before then.
Does Bsr Projects file quarterly progress reports with RERA?
2 of 2 running registrations approved before 1 Oct 2025 have filed a quarterly progress update.